Yes you are rigth...my program only have the activities, the duration, the relationships and the resources but don’t have the cost...that last, but the price of the contract is global...
So, i tried to use excel to get the percent value of each activitie based in the duration of the same...on friend tell me the follow..."you can use the sum of the duration of all activities...if project show you 125 days...and you get 235 days but the sum don’t worry...cause that is the number of day to complete the project...but you have to take present something...some activities have duration underhand one over one..."
I tried to see your picture on imageshack but could not.
Also, I am not sure that I understand from your description exactly what your problem/issue is.
However, I will try to figure it out.
So you have no resources and no costs assigned to the tasks.
You attempt to calculate something called "percent value" which is the duration of a task divided by the total duration of the project.
But of course this does not work, or at least does not produce anything which means something or is useful.
A simple example might be 100 one-day tasks all happening on day 1 of the project. The total duration is just 1 day and the duration of one task divided by one day is 1 (or 100%) and the sum of the percents is 100 x 100% = 10,000%.
What does it mean? Nothing, really.
Have you tried assigning a resource to the tasks?
You could call it "One Day", and give it a cost of $1/Day.
Then you would have cumulative Work or cumulative Cost as a proxy of cumulative days.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Trevor.
Yes you are rigth...my program only have the activities, the duration, the relationships and the resources but don’t have the cost...that last, but the price of the contract is global...
So, i tried to use excel to get the percent value of each activitie based in the duration of the same...on friend tell me the follow..."you can use the sum of the duration of all activities...if project show you 125 days...and you get 235 days but the sum don’t worry...cause that is the number of day to complete the project...but you have to take present something...some activities have duration underhand one over one..."
This is real?...
Thanks
I tried to see your picture on imageshack but could not.
Also, I am not sure that I understand from your description exactly what your problem/issue is.
However, I will try to figure it out.
So you have no resources and no costs assigned to the tasks.
You attempt to calculate something called "percent value" which is the duration of a task divided by the total duration of the project.
But of course this does not work, or at least does not produce anything which means something or is useful.
A simple example might be 100 one-day tasks all happening on day 1 of the project. The total duration is just 1 day and the duration of one task divided by one day is 1 (or 100%) and the sum of the percents is 100 x 100% = 10,000%.
What does it mean? Nothing, really.
Have you tried assigning a resource to the tasks?
You could call it "One Day", and give it a cost of $1/Day.
Then you would have cumulative Work or cumulative Cost as a proxy of cumulative days.