Thats the correct way of managing EPS and Projects. In P6 you have an option if you wanted to ignore relationship to and from project whether open or not. You can run resource leveling for all projects by opening the EPS and not the individual project alone. You can all run separately for special purpose if you need to. I cannot see any technical difficulties as P6 was design to run by enterprise or by individual project.