Hi mimoune

in fact P3 calculate the average of ressources (la moyenne des ressources).



A+

R
Rodel Marasigan 👤 Member for 19 years 7 months

Mimoune,

P3 calculate resource percent complete by resource proportion or weightings.

ex:Act1 have 2 resource with diff resource % complete

R1 = 40 units * 20% = 8 unit

R2 = 80 units * 25% = 20 unit

R/C % complete = (8+20)/(40+80) = 23.33% or 23%

M
mimoune djouallah 👤 Member for 19 years 7 months

thanks craig



what i don’t understand is when you show resource percent complete on a column, and you have two resources assigned to one activity, how P3 calculate the percent complete for the two resource together !



best regards

Mimoune

C
Craig Brough 👤 Member for 23 years 7 months

Hi



I have not P3 open right now but here is a starter for 10 (or 2):



Group & Sort by resource and set the columns to display % complete.



Or, Export activity data grouped by resource. Export Total budget Quantity, Actual, and remaining and you can derive % Complete from this



Hope this helps.



Craig

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts