What is the best way to do a revised program.With Actual dates and data date the date of revising the schedule or revised schedule without actual dates and data date project start date.
What is the forum consensus
Kumar,
It depends on your intention, approach and how you wanted to show your baseline. (Below link are some discussion on re-baseline for your reference)
How to set Baseline- After revised the Schedule and to
Baseline with actual dates in
Baseline Date Problem
Rodel,
The clarification required is in primavera do you input actual dates for the completed /inprogress activities upto the schedule revision date and use the same as date date .In this case while scheduling there will not be a closed loop and is there possibilities for errors.
On the other hand the hand is it not better to have the data date as the project start date and revise the schedule without any actual dates.
Kumar,
Like what I have said as long as it is accepted by the client then it should be fine.
Yes it is a general practice and Re-Baseline means reflection of Actual plus remaining activities which may have different logic, target & finish date. It is an update of previous baseline and a result of crushing or new construction methodology is being applied to show more reliable baseline. You should explain the reason why re-baseline is required and basis of schedule for the new baseline to convince the client.
What is the used of new baseline if that is far from the actual history of a project?
Hi,
Thanks for your reply.You mean it is the general practice to update the schedule with actual dates till the date of schedule revision and revise the remaining part.To summarise revised schedule with actual dates and with data date,the date of schedule revision and not the project start date is acceptable
Kumar,
Normal practice of re-baseline is reflection of Actual plus the remaining activities which shows the history of the project. As long as it was agreed by the clients, it should be fine. You should also include the reason of re-baseline and Basis of Schedule revision to buy-in the client.