Baseline dates problems

R
Rodel Marasigan 👤 Member for 19 years 7 months

Paul,

Thanks for the information and I always using that function but doesn’t solve the problem because it still follow the old logic from the baseline and will still show slippage. The only way is to change the planned date with current date and don’t run the schedule (F9). That will give exact replica of current schedule and save as a baseline. Meaning original duration will change and follow the current duration which will not the same if "Budgeted Value with current date" is used.

P
Paul Silver 👤 Member for 21 years 8 months

Huzzle and Rodel,



There is a simpler way of overcoming this problem. In Admin Preferences under the Earned Value Tab, the Earned Value Calculation default is "Budgeted values with planned dates".



If you have the necessary authority, change this to the "Budgeted values with current dates" option. If you don’t have the authority you will need to discuss this with your system administrator. When you have made the change, copy your current project and assign it as a baseline and the dates will be aligned (as you would expect).



I hope this is of some assistance.



Regards

Paul Silver


Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts