MSP only does one thing with ALAP and that is that it sucks all of the float out of the entire path that the task is on. This is a bit unexpected since usually people expect to see it go only as late as for it to use up only its own float. But ALAP is not a "zero free float" constraint as in P3. ALAP makes sense but is rarely used except in special situations because:
It is too strong for what is usually intended.
It is not consistent with the critical path method.
Hi Guys, Alexandre how are you going? Microsoft Project apparently does some funny things with ALAP. I can demonstrate to all of you how Asta Powerproject does it if this would be useful?
These tasks are under therir own summary, and the schedule works for the planning stage am thinking to change the links once the work starts and have ithem driven the normal way then.
Can send you the file if you would be kind enough to review and give me comment.
Sometimes it is better not to link tasks that have no relevance to linked tasks.
Operations such as "Sales" can be set up as a hammock task covering the programme tasks that are relevant.
A hammock can be set up by placing milestones in a section of the chart and linking them ASAP to the relevant tasks and then indenting them into a summary.
The Sales hammock will then shadow the the programme.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
MSP only does one thing with ALAP and that is that it sucks all of the float out of the entire path that the task is on. This is a bit unexpected since usually people expect to see it go only as late as for it to use up only its own float. But ALAP is not a "zero free float" constraint as in P3. ALAP makes sense but is rarely used except in special situations because:
It is too strong for what is usually intended.
It is not consistent with the critical path method.
Hi Guys, Alexandre how are you going? Microsoft Project apparently does some funny things with ALAP. I can demonstrate to all of you how Asta Powerproject does it if this would be useful?
Alexandre,
These tasks are under therir own summary, and the schedule works for the planning stage am thinking to change the links once the work starts and have ithem driven the normal way then.
Can send you the file if you would be kind enough to review and give me comment.
Kind regards,
Craig Adams
Mike,
Thank you for your reply, can you imbed an example or email to me, not sure about how to use hammock tasks or how they work.
Kind regards,
Craig
Hello Mike and Craig,
problem is: MS Project does not know what a hammock task is; so Craig is back where he started
Personally I would identify each phase as a separate summary activity, being not linked to any other
Alexandre
Hi Craig
Sometimes it is better not to link tasks that have no relevance to linked tasks.
Operations such as "Sales" can be set up as a hammock task covering the programme tasks that are relevant.
A hammock can be set up by placing milestones in a section of the chart and linking them ASAP to the relevant tasks and then indenting them into a summary.
The Sales hammock will then shadow the the programme.
Best regards
Mike Testro