To update the Project and move the bars of activities that dont start or finish to programmed date select Tools-> Tracking->Update Projects. Tick Reschedule uncompleted works to start after (enter the status date or cut-off) then click Ok.
To show the status line, right click on the Gantt chart area and select Gridlines then find Status Line. Change the type to solid line or any presentation you want to see on the screen. Change the color to blue or any color you wanted and click Ok.
Hi Rodel Thanks 4 the information....well, i continue waiting the help to the second part of my original post = "And How i can create or use the state line, when i wanna know or see in the screen of muy work bars the displace of the activities if it don’t start or finish to the programmed date?."
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Jhorbam,
To update the Project and move the bars of activities that dont start or finish to programmed date select Tools-> Tracking->Update Projects. Tick Reschedule uncompleted works to start after (enter the status date or cut-off) then click Ok.
To show the status line, right click on the Gantt chart area and select Gridlines then find Status Line. Change the type to solid line or any presentation you want to see on the screen. Change the color to blue or any color you wanted and click Ok.
Hi Rodel Thanks 4 the information....well, i continue waiting the help to the second part of my original post = "And How i can create or use the state line, when i wanna know or see in the screen of muy work bars the displace of the activities if it don’t start or finish to the programmed date?."
THANKSSSSS
Jhorbam,
Select Tools-> Change Working Time
Under For: change to Night Shift then change the working time per shift - From and To as required
Note: MSP dont accept passing to 12:00 oclock cycle twice:
Ex: 6:00 AM to 2:00 PM - 2:00 PM to 10:00 PM - 10:00 PM to 12:AM only because exceeding to that is another day.
If required different from working hour you need to create different calendar for each shift allocated on each resource.
Hi...well i wanna create the follow.
Shift 1. 6am to 1:59pm
Shift 2. 2pm to 9:59pm
Shift 3. 10pm to 5:59am
And i wanna have the 3 shifts working the same day...i tried but Project dont save the changes in my calendar.
Well...Can someone help me?
Have you saved a Baseline?
Have you seen the Tracking Gantt View and the Tracking Table?
Dear J,
The working hours (shift) is specified in the Calender.
With kind regards,
Samer