Oracle Primavera - PM6 Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Sun, 2010-04-18 19:36 Permalink RE: Early Start/Finish S-curve vs Baseline S-curve Christina, Baseline dates are different from start/ finish date if you have any assigned to current in progress program. Member for 18 years 3 months Member for 18 years 3 months Submitted by PINAN T. on Sun, 2010-04-18 14:09 Permalink RE: Early Start/Finish S-curve vs Baseline S-curve Without update Start/Finish date equals Early Dates equals Planned Dates Log in or register to post comments
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Sun, 2010-04-18 19:36 Permalink RE: Early Start/Finish S-curve vs Baseline S-curve Christina, Baseline dates are different from start/ finish date if you have any assigned to current in progress program.
Member for 18 years 3 months Member for 18 years 3 months Submitted by PINAN T. on Sun, 2010-04-18 14:09 Permalink RE: Early Start/Finish S-curve vs Baseline S-curve Without update Start/Finish date equals Early Dates equals Planned Dates
Member for
19 yearsRE: Early Start/Finish S-curve vs Baseline S-curve
Christina,
Baseline dates are different from start/ finish date if you have any assigned to current in progress program.
Member for
18 years 3 monthsRE: Early Start/Finish S-curve vs Baseline S-curve
Without update
Start/Finish date equals Early Dates equals Planned Dates