•Select the top panel by clicking in it somewhere. You know it is selected because the bar on the far left containing the name of the view turns darker.
•Go to the view menu and select view - resource sheet.
•Select the bottom panel by clicking on it somewhere.
•Again go to the view menu and select the resource graph view.
•Right click on the resource graph area on the right.
•From the menu that pops up choose "Format Barstyles"
•On the left half of the dialog box that appears (the part marked "Selected Resources") set the "Show as:" BAR or anything except than "Don’t Show".
•On the right half of the dialog box that appears (the part marked "Resources") set the "Show as:" Don’t Show.
•Click OK until you are back to where you started.
•Now select or highlight all resources in the top panel and the chart for all of those selected resources will be shown in the bottom panel.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Samer,
Sorry I don’t have. My answer is only based on my knowledge and experience.
Best Regards,
Rodel
Dear Rodel,
Do you have contacts with MS Project People. Maybe you can ask them to have presence on PP so that they can answer questions immediately.
With kind regards,
Samer
Rodel, thank you very much for your help, you have been an immense support.
I have carried out your instructions and it has worked perfectly for what i wanted.
Once again, thank you very much.
Jamie,
Below are the steps how.
•From the window menu select "split"
•Select the top panel by clicking in it somewhere. You know it is selected because the bar on the far left containing the name of the view turns darker.
•Go to the view menu and select view - resource sheet.
•Select the bottom panel by clicking on it somewhere.
•Again go to the view menu and select the resource graph view.
•Right click on the resource graph area on the right.
•From the menu that pops up choose "Format Barstyles"
•On the left half of the dialog box that appears (the part marked "Selected Resources") set the "Show as:" BAR or anything except than "Don’t Show".
•On the right half of the dialog box that appears (the part marked "Resources") set the "Show as:" Don’t Show.
•Click OK until you are back to where you started.
•Now select or highlight all resources in the top panel and the chart for all of those selected resources will be shown in the bottom panel.
Sorry Rondel, I never explained myself properly.
Is there a way of displaying multiple resources within the graph and not just individual graphs for each resource?
Thanks.
Jamie,
What do you mean by single graph? If page then change the timeline.
Thanks for your help Rodel.
Is there anyway of getting all the information presented in 1 single graph?
Thanks.
Jaime,
Select View-> Resource Graph. If not satisfied right click the graph and select on different presentation like cummulative, work, remaining etc...