•Select the top panel by clicking in it somewhere. You know it is selected because the bar on the far left containing the name of the view turns darker.
•Go to the view menu and select view - resource sheet.
•Select the bottom panel by clicking on it somewhere.
•Again go to the view menu and select the resource graph view.
•Right click on the resource graph area on the right.
•From the menu that pops up choose "Format Barstyles"
•On the left half of the dialog box that appears (the part marked "Selected Resources") set the "Show as:" BAR or anything except than "Don’t Show".
•On the right half of the dialog box that appears (the part marked "Resources") set the "Show as:" Don’t Show.
•Click OK until you are back to where you started.
•Now select or highlight all resources in the top panel and the chart for all of those selected resources will be shown in the bottom panel.
Member for
15 years 9 months
Member for15 years9 months
Submitted by Jamie Clarke on Wed, 2010-04-14 10:21
Member for
19 yearsRE: How do i create a Resource Profile in MSP?
Hi Samer,
Sorry I don’t have. My answer is only based on my knowledge and experience.
Best Regards,
Rodel
Member for
17 years 3 monthsRE: How do i create a Resource Profile in MSP?
Dear Rodel,
Do you have contacts with MS Project People. Maybe you can ask them to have presence on PP so that they can answer questions immediately.
With kind regards,
Samer
Member for
15 years 9 monthsRE: How do i create a Resource Profile in MSP?
Rodel, thank you very much for your help, you have been an immense support.
I have carried out your instructions and it has worked perfectly for what i wanted.
Once again, thank you very much.
Member for
19 yearsRE: How do i create a Resource Profile in MSP?
Jamie,
Below are the steps how.
•From the window menu select "split"
•Select the top panel by clicking in it somewhere. You know it is selected because the bar on the far left containing the name of the view turns darker.
•Go to the view menu and select view - resource sheet.
•Select the bottom panel by clicking on it somewhere.
•Again go to the view menu and select the resource graph view.
•Right click on the resource graph area on the right.
•From the menu that pops up choose "Format Barstyles"
•On the left half of the dialog box that appears (the part marked "Selected Resources") set the "Show as:" BAR or anything except than "Don’t Show".
•On the right half of the dialog box that appears (the part marked "Resources") set the "Show as:" Don’t Show.
•Click OK until you are back to where you started.
•Now select or highlight all resources in the top panel and the chart for all of those selected resources will be shown in the bottom panel.
Member for
15 years 9 monthsRE: How do i create a Resource Profile in MSP?
Sorry Rondel, I never explained myself properly.
Is there a way of displaying multiple resources within the graph and not just individual graphs for each resource?
Thanks.
Member for
19 yearsRE: How do i create a Resource Profile in MSP?
Jamie,
What do you mean by single graph? If page then change the timeline.
Member for
15 years 9 monthsRE: How do i create a Resource Profile in MSP?
Thanks for your help Rodel.
Is there anyway of getting all the information presented in 1 single graph?
Thanks.
Member for
19 yearsRE: How do i create a Resource Profile in MSP?
Jaime,