Updated prgram as baseline program

S
Shah. HB 👤 Member for 17 years 6 months

Hi vinod



You can treat the updated schedule as target.Make sure the existing pro-gramme[Which you use for monitoring ] and target should not have same file name.Make sure your target and existing pro-gramme are in one folder

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi Vinod,

Open the project that you wanted to save as target.

Select Tools->Project Utilities->Copy. Once copied, Select Tools->Project Utilities->Target, select the project copied.



Note: Only 2 projects can be display at the same time. If already have 2, replace any one of them.