How to set Baseline- After revised the Schedule and to

A
abbas india 👤 Member for 16 years 10 months
I
Iyke Nwosu 👤 Member for 8 years 11 months

Dear Abbas,

when you want to maintain your baseline, selecting "Save a copy of the current project as baseline" will maintain the baseline based on that very project, to correctly select the right baseline, choose the second option "Convert another program.........", make sure to have imported the baseline program and select the program, Assigne afterwards. Re-schedule and your actual dqate will return.

 

Regards

Iyke Nwosu

A
abbas india 👤 Member for 16 years 10 months

During revision itself we will have actual dates in i!!



The same file is taking a copy and assigning as baseline but it loosing the actual dates.



Abbas

F
Ferdinand U. 👤 Member for 18 years 10 months

you need to use global change for activity status equals in progress and completed before assigning as baseline

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts