Dear Abbas,
when you want to maintain your baseline, selecting "Save a copy of the current project as baseline" will maintain the baseline based on that very project, to correctly select the right baseline, choose the second option "Convert another program.........", make sure to have imported the baseline program and select the program, Assigne afterwards. Re-schedule and your actual dqate will return.
Regards
Iyke Nwosu
http://www.planningplanet.com/forum/forum_post.asp?fid=&Cat=8&Top=50178
During revision itself we will have actual dates in i!!
The same file is taking a copy and assigning as baseline but it loosing the actual dates.
Abbas
you need to use global change for activity status equals in progress and completed before assigning as baseline