Crane Time Analysis
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Chris.
The only software you need is a spreadsheet.
See my earlier response and you will get the formula.
Best regards
Mike Testro
Is there any software to simplify this hook time process. I urgently need justify the use of 3 cranes on a 3 year project.
Hi I cannot seem to find any software that helps with hook time analysis, Is there any software??
Guys new Towercrane hook analyis for sharing
Hi Danang
See my previous thread which gives you the formula.
Best regards
Mike Testro
Hi there,
Is there any standard formula or rule of thumb for calculating the crane hook time analysis? Also what factor need to be included on crane time for the crane cannot be used due to the weather? Please advise.
Regards,
Dan
Hi KS
As in all transport plant productivity you need to calculate 3 things:
1. Load time
2. Travel time x 2
3. Discharge time
With these numbers you can calculate the number of journeys in a work day shift - allow 80% efficiency/downtime.
In a tower crane this is sometimes called hook time.
You can then calculate the number of lifts that is needed in a work day shift and if that exceeds the hook time then your crane will be the productivity limit.
Time to consider an extra crane.
Best regards
Mike Testro
Dear Anoon,
I have not carried out any studies on other model tower crane, thus I can’t say LB200 is a F1 or Fx. I would be interested if you have any researches on this issue.
It is obviously that the crane time analysis is to study the crane not the concrete pump. You have mentioned the bucket for concreting. Yes, bigger size bucket could improve the time figure. For this analysis, it was a 2cum bucket.
The time to fix P/C elements in position has been taken into consideration in this analysis.
Regards,
KS
Dear Gary,
From my experience this is supplier dependent. If you can get the model of the Crane, you can download the charts of the crane from the supplier website. This is standards.
Then you can figure out the loads and the distances. This is the minimum that you can do at major sites for HSE approvals.
If you have a special lift, please let me know, I might be able to assist.
With kind regards,
Samer
Dear,
Is there any software for crane analysis?
Gary
Dear KS,
90 Meters high building + unidentified Liebherr crane type, identified lift height not known your production rates are too high.
It would be advisable if you discuss this with your construction crews and using the www.Liebherr.com data sheets.
With kind regards,
Samer
KS,
maybe you got an F1 crane, for concrete placement, youll need a bucket (crane and bucket), I supposed your rate is for concrete pump?
for precast element, your crane will hold the element until fixed (dependent on the sizes and fixes/anchors)