In P6 Web tool, you go under the Resource Heading and select Manage Team.
You can then define the resoruce team as you wish and use it for dashboard presentation and high level resoruce planning using the P6 web what-if enhanced capacity.
Is a great tool. I just start to have a look at it, and it is worth it.
I do not know if I understood u but if u r going to manage resources through resources can’t be u have to manage recourses through OBS . THIS WHAT DID U MEAN OR STILL NOT?
regards.
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Sat, 2010-03-20 07:56
if I understand you well, you want to manage the resources by hierarchical groups the same way you can manage activities by WBS level
Go to Resources, create a 1st level of resources that will be your groups, say "Carpenters"; then create new resources under this first one, and click the Indent button (small black arrow head on the right side of the screen) to push the individual resource inside the group, say "Joseph" is part of the "Carpenters" group.
When you open your new project, you define the "Access Mode", the lowest menu on the Open project. You have three options: Exclusive, Sharee, and read only. If you double click on the project, then you will open up the default.
Member for
22 years 3 monthsRE: Resource Team in P6V7
Hi
In P6 Web tool, you go under the Resource Heading and select Manage Team.
You can then define the resoruce team as you wish and use it for dashboard presentation and high level resoruce planning using the P6 web what-if enhanced capacity.
Is a great tool. I just start to have a look at it, and it is worth it.
L
Member for
15 years 8 monthsRE: Resource Team in P6V7
dear :
can u tell us how ?
regards
Member for
22 years 3 monthsRE: Resource Team in P6V7
Update
I found it
It can be defined in P6 web tool
is not a client/server funcionality
Cheers
Luca
Member for
15 years 8 monthsRE: Resource Team in P6V7
Dear luca:
I do not know if I understood u but if u r going to manage resources through resources can’t be u have to manage recourses through OBS . THIS WHAT DID U MEAN OR STILL NOT?
regards.
Member for
22 years 9 monthsRE: Resource Team in P6V7
Luca,
if I understand you well, you want to manage the resources by hierarchical groups the same way you can manage activities by WBS level
Go to Resources, create a 1st level of resources that will be your groups, say "Carpenters"; then create new resources under this first one, and click the Indent button (small black arrow head on the right side of the screen) to push the individual resource inside the group, say "Joseph" is part of the "Carpenters" group.
Hope it helps,
Alexandre
Member for
22 years 3 monthsRE: Resource Team in P6V7
Hi
I may have been miss-understood
I know how to assign resource.
In P6 Web tool there is an applet that allow to manage resoruce assignment by resoruce as well as by resource group
I tried the roles, but it is not recognised as a resoruce group.
Could please advice if you know how to assign a pool of resource as a resource group/team?
Cheers
L
Member for
17 years 3 monthsRE: Resource Team in P6V7
Dear Luca,
You open the file and then go the the activities button on thee menu on your left and then you start adding Resources on the menu on your right.
Or you go the each activity and highligth it then you add the Resource that you want.
With kind regards,
Samer
Member for
22 years 3 monthsRE: Resource Team in P6V7
Hi
is not quiet what I was asking
with P6 Web you can display resource teams, but I am not able to create them.
Cheers
Luca
Member for
17 years 3 monthsRE: Resource Team in P6V7
Dear Luca,
When you open your new project, you define the "Access Mode", the lowest menu on the Open project. You have three options: Exclusive, Sharee, and read only. If you double click on the project, then you will open up the default.
With kind regards,
Samer