Need Help on Hospital Schedulling

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Ruel,



Very chanllenging project, congradulations.



The problems with operational site is that you have to adhere to the Operator’s rules and conditions. So the constraints are very much real and very much affecting your works.



The basics for making a schedule does not change. The scope is known in your BOQs, drawings and specifications. The issue here is the zoning and planning that is going to take place to complete the works.



So I suggest that you hold a few meetings (say 3) within 1 week with your team, and especially the operator, security, quality control, and any other existing entity at the Lab that might affect your Schedule, and start discussing the zone and what you are going to do. Sketch up some WBS during the meeting, then after few meeting, send it to the Engineer for Approval.



Once your WBS and method statements are approved, you can start the Scheduling as usual.



About the zero noize and zero dust. Either you keep it to an acceptable minimum or you submit a quality procedure to ensure that and get it approved by your Engineer.



With kind regards,



Samer

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts