Arnold Puy 👤 Member for 19 years 1 month

Hi Anbin,



Perhaps the problem is within the creation of your new Resource Curve. I am not quite sure what you have done, but anyway, you solve your own problem. You discover something.



Regards,



Arnold

A
Anbin Ponnith 👤 Member for 17 years

Dear Sir,



First I created a resource curve for each activity and assigned to all resources regardless of the pay item.But I faced problem in the cost.



Now I have created separate resource curves for each pay item and assigned and updated the cost comes correct.



for example,

for the electrical activity with the pay items,

1.Conduits

2.Cables.

3.Switches & Lights.

Previously I have assigned a common resource curve for all the pay items above.But the problem was not fixed.

Now I have created separate resource curve for each pay items & assigned the problem got fixed.



Is that the procedure.Am I doing correct.





with Thanks & Regards,



Anbin Ponnith

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Anbin,



Try to check your Duration Type. It should be Fixed Duration & Units. What Resource Curve did you assign?



Regards,



Arnold

A
Anbin Ponnith 👤 Member for 17 years

Dear Sir

Thanks For ur Reply

I am working for a Project of 226 Villas.The Client told us to Have only 10 Activities Per Villa.

1.Substructure

2.SuperStructure

3.Roof WaterProofing

4.Mechanical Hvac

5.Mechanical Plumbing

6.Electical & All System

7.Civil Finishes

8.Doors & Windows

9.Specialities,Wood & Plastic

10.Site Preparation & Boundar Wall

For Mechanical HVAC,Mechanical Plumbing & Electrical I dont want the Cost to be Distributed Uniformly,So that i Create a new Resource Curve Mechanical HVAC & Modify it

After that I Select the Activity Mechanical HVAC Click Activity Detail->Resource Tab->Curve

I Assigned Curve to all Resource Assigned to That Activity

After Assigning The Curve if i Saw The Budgeted Cost it Getting Changed

Regard

Anbin

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Anbin,



If I understood you correctly, you assigned Curve to your Activities and not to the Resources.



As far as I know, if you assigned a curve, only the cost distribution per day/week/month will change according to the assigned Resource Curve but not the Budgeted Cost. Correct me if I am wrong.



What did you do, can you elaborate further.



Regards,



Arnold

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts