You are welcome Salman.
Thanks a lot Arnold
Hi Salman,
There are two alternatives that you can perform.
1. You can do this by updating the baseline. But, be careful with this because it is a little bit complicated and dangerous. Always create backup to your schedule.
2. By restoring your baseline and do the necessary modification as what you have done to your current schedule. This is safe but time consuming.
Regards,
Arnold
Hi Arnold,
I appreciate your very valuable replies.Thanks a lot for that.
If I add activities in my current schedule and I want them added to the baseline along with their relation ships, res.,What shall be the procedure for this.
Hi Wafa,
Since you copy and paste the project then modified it, it doesnt influence the others. However, if you delete some activities it will affect the project but it does not affect the baseline schedule.
Regards,