Hi Satishan,
1. Try to use the Edit --> Replace
2. Open the two projects and go to Activity Codes then Copy & Paste the codes.
3. Copy the projects and in the "Copy Activity Option" untick the check box next to Relationships.
Regards,
Arnold
Hi Satisham
Q 1.
I do not use P6 but if I want to make a global change to anything in Powerproject I copy paste the column into excel and then use Find - Replace to make the changes then copy it back.
No idea at all about Q 2 & 3.
Best regards