Thanks for your reply,



I have assigned 2 Baselines Primary & secondary (BL1 & BL2). In the Percent complete coloumn selection view I cannot see the BL2 values.



Is there any way to view the differences of the % completes from Baselines ( This baseline is secondary BL which is Last week updated schedule) & current schedule so that I can know the weekly progress.