Thanks Samer
Dear Shahul,
I found this website with the following definition:
http://www.downloadpipe.com/Windows/business-project-management/review-…
"
Q. Scheduling is quantitative scheduling in the context that quantities to be executed at different locations of the construction project form the elements of the schedule. Also Q. Scheduling is Queue Scheduling in the context that trades pass through the different segments of the project in a queue sequence. No interference between two activities is allowed at the same location. It is derived basically from the Line of balance technique with... "
With kind regards,
Samer
Q for Quantitative ,is it correct ?
Hi
What does Q stands for ?
Dear Rafael,
If it can generate a 10% savings on 5 locations, then we better learn how to use it :)
With kind regards,
Samer
Sammer,
The problem with this approach is that it will delay the start of some activities in order to keep them together while it is desirable to have some float especially on earthwork activities.
Q Scheduling software is limited to consider up to 5 locations so it is quite limited. I wonder if serious scheduling can be done with such software.
Best regards,
Rafael