Many thanks Ian, I made the first option.
Two options:
1) If you go to the activity assignments module, you can put that checkbox into a column, uncheck the first one and use Edit/Fill Down (CNTRL-E) to populate the rest.
2) Run a Global Change with the Subject Area set to activity resource assignments to clear the checkbox.