A Baseline is a comparison reference, it can be a contractual approved baseline, the original or an approved revision, it can also be a reference to a “what if” reference job looking into possible alternatives to recover your schedule, it can be a non contractual baseline as for example your prior update as to compare progress between updates.
In MS Project all baseline data is stored in the same project file contrary to other software, but you can save every update as a separate file, and you should. You have to be careful about your baselines; MS Project is tricky if you make an update of your job and then have to add an approved baseline with a data date prior to your last update as you can only add to baselines your current job. You can copy and paste data from two versions of your job so you can get Baseline Data transferred this way, time consuming but can be done.
The is the definition stated in the Standard Practice Standard for Scheduling issued by the Project Management Institute:
Baseline: The approved time phased plan (for a project, a work breakdown structure component, a work package, or a schedule activity), plus or minus approved project scope, cost, schedule, and technical changes. Generally refers to the current baseline, but may refer to the original or some other baseline. Usually used with a modifier(e.g. cost baseline, schedule baseline, performance measurement baseline, technical baseline).
In short, it is what the Engineer approves at the start of the project.
As in all software a "baseline" is a snapshot of the programme held in a different file which will underly the tasks and show the differences when changes are made.
In delay analysis the Baseline is the original contract programme before events are impacted.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
A Baseline is a comparison reference, it can be a contractual approved baseline, the original or an approved revision, it can also be a reference to a “what if” reference job looking into possible alternatives to recover your schedule, it can be a non contractual baseline as for example your prior update as to compare progress between updates.
In MS Project all baseline data is stored in the same project file contrary to other software, but you can save every update as a separate file, and you should. You have to be careful about your baselines; MS Project is tricky if you make an update of your job and then have to add an approved baseline with a data date prior to your last update as you can only add to baselines your current job. You can copy and paste data from two versions of your job so you can get Baseline Data transferred this way, time consuming but can be done.
Dear frederick,
The is the definition stated in the Standard Practice Standard for Scheduling issued by the Project Management Institute:
Baseline: The approved time phased plan (for a project, a work breakdown structure component, a work package, or a schedule activity), plus or minus approved project scope, cost, schedule, and technical changes. Generally refers to the current baseline, but may refer to the original or some other baseline. Usually used with a modifier(e.g. cost baseline, schedule baseline, performance measurement baseline, technical baseline).
In short, it is what the Engineer approves at the start of the project.
With kind regards,
Samer
Hi Frederick
As in all software a "baseline" is a snapshot of the programme held in a different file which will underly the tasks and show the differences when changes are made.
In delay analysis the Baseline is the original contract programme before events are impacted.
Best regards
Mike Testro