We developed a utility for one of our clients that would do this and put the result into a UDF when transferring WOs from Maximo. It would show successor id (lag).
You could probably do the same thing using the export to excel function, including the resource lags, do a VLOOKUP (or write a macro) to populate a UDF at the activity level and then re-import the data.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
There is no way to do this in P6 out of the box.
We developed a utility for one of our clients that would do this and put the result into a UDF when transferring WOs from Maximo. It would show successor id (lag).
You could probably do the same thing using the export to excel function, including the resource lags, do a VLOOKUP (or write a macro) to populate a UDF at the activity level and then re-import the data.
Ian
http://www.emerald-associates.com
Hi
Rafael ,i tried in P3 but it doesnt works {as sure track is lower version of P3}
Did you tried Organize by Sucessor/Predecessor and see if the field is available?

Sorry I do not have P6 but the idea comes from my experience with SureTrak, this allowed me to see lag and filter for it while in the layout.