Actually P3 has problems with converting MS Project mpx. That is why we created separate P3 mpx export/import.

Besides it is necessary to avoid linking phases (summary tasks) in MS Project if it is planned to convert the schedules into other software.

Best Regards,

Vladimir

R
Rafael Davila 👤 Member for 22 years 4 months

P6 should be able to read MPP files.

P3 reads older MPX file format but not MPP, you need a converter to convert MPP to MPX.



All file conversions can create problems but converting form MPX/MPP to P3/P6 is less problematic than going the other way. For example MS Project does not allows two links to the same predecessor while 3/P6 does. Therefore P3/P6 will have no problem with these links while MS Project will.

Featured Partner

Top Posters

jeoffrey reyes
15 posts
Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts