I expected that you will get the answer to set activity effort and assign your resources. For effort driven activity the duration is calculated basing on the number and calendars of assigned resources.
This problem is usual in projects. In Spider Project we use different technique, defining quantity of work, resource productivities, mimimal and maximal quantities of assigned resources. The software calculates planned duration basing on these data.
I hear what you say you are hoping for, but is it not better to just make a proper model and solve the problem by working with the tool the way it is designed to be used?
What I would do.
Chop the task up into 8 x 5 days tasks.
Create the 13 resources and assign them as required to the tasks.
Level first with all options turned off, then try other options one at a time.
You can send me the file so I know what we are talking about. I am on skype.
I was hoping to be able to accept work calling for +13 resources and have the software calculate an end date taking into account the resource overload.
The settings in the Resource Leveling/Leveling Order: have boxes 2 & 3 checked.
I do have the max units on the Resource Sheet set to 13. Im wanting MS Project to "automatically" stretch the timeline to 40 days to work the request.
Stretching the bar out to 40 days is not desirable as Ill be handing this file off to others to move forward with.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thank you Vladimir and all,
I believe I have exhausted all investigations and have used all input.
Thank you for a satisfactory conclusion.
Eric
I expected that you will get the answer to set activity effort and assign your resources. For effort driven activity the duration is calculated basing on the number and calendars of assigned resources.
This problem is usual in projects. In Spider Project we use different technique, defining quantity of work, resource productivities, mimimal and maximal quantities of assigned resources. The software calculates planned duration basing on these data.
Best Regards,
Vladimir
Trevor,
Thanks for the help. I had decided to chop up the task but had hoped that I was overlooking something.
Be well,
Eric
Eric,
I hear what you say you are hoping for, but is it not better to just make a proper model and solve the problem by working with the tool the way it is designed to be used?
What I would do.
Chop the task up into 8 x 5 days tasks.
Create the 13 resources and assign them as required to the tasks.
Level first with all options turned off, then try other options one at a time.
You can send me the file so I know what we are talking about. I am on skype.
Thanks, Trevor.
I was hoping to be able to accept work calling for +13 resources and have the software calculate an end date taking into account the resource overload.
The settings in the Resource Leveling/Leveling Order: have boxes 2 & 3 checked.
"automatically" stretch the timeline to 40 days"
Wont happen, cant happen, should not happen.
The basic problem here is that the task is too long and has too many resources assigned. If you chop things up a bit, all problems will disappear.
What leveling options do you have checked in Tools, Level Resources?
Thank you, Mike
I do have the max units on the Resource Sheet set to 13. Im wanting MS Project to "automatically" stretch the timeline to 40 days to work the request.
Stretching the bar out to 40 days is not desirable as Ill be handing this file off to others to move forward with.
Go well,
Eric
Hi Eric
Set the maximimum resource allowed at 13.
Otherwise just stretch the bar to 40 days and be done with it.
Best regards
Mike Testro