To make the information useful to our friend who asked, the summary is that in order to determine the productive rates, the following parameters must be determined:
1. Type of Machines used (size, age, condition).
2. Type of soil and terrain.
3. Method/ Sequence of work.
4. Of course worker productivity is alawys an issue.
This is a standard question in most Engineering Economy books.
Better double chek it is not a a 7-inch 45 rpm Tom Jones record.
I know Tom Jones was a British singer of the 70’s but we never watched the show. It was shown at the same hour a local singer was on TV. My mother always wanted to see the show but at home we practiced democracy where majority rules. My one years old younger brother would say, Mom, the only word he knew. My father would say local talent and so do I, we always won by the count of 3 to 1.
I worked with a bulk earthworks contractor in the UK for 3 years in the late 1980s.
It was when I first used lotus 123 to its full potential in developing an average mass haul calculation matrix for cut to fill volumes.
I still have the original somewhere but it is on one of those big acetate floppies.
It was when I was developing a record keeping system that required the foremen to write a simple 3 digit code against each earth movement that I learnt my nickname - The Fat Controller.
Very good point, your scientific approach is the correct. Production rates are not fixed.
Even when new scrapers are faster than the older they are somewhat limited, in adittion to the fact new trucks and backhoes are becoming also more efficient. We use them frequently here as our landscape is 75% mountains, on our road design and construction we accommodate for minimum hauling distances, grade-ability becomes a major concern even when empty up the hill.
Good production references should provide you with different scenarios and combination of equipment as to simplify your preliminary estimate. That is why I advocate for references that provide you with the details; usually a brief description of the operation and the crew that includes equipment will do it. This is what is missing at the production rates shown in PP, if neither crew nor methods are provided production can be anything.
Gobinath question is in order, he cannot deppend on production rates as shown in PP.
I would also recommend that you check the type and size of machine that you will have on site. This is a Major Factor in determining the productivity rates.
Generally, the bigger the machines, the higher the productivity rates depending on the type of site layout you have.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Guys,
To make the information useful to our friend who asked, the summary is that in order to determine the productive rates, the following parameters must be determined:
1. Type of Machines used (size, age, condition).
2. Type of soil and terrain.
3. Method/ Sequence of work.
4. Of course worker productivity is alawys an issue.
This is a standard question in most Engineering Economy books.
With kind regards,
Samer
Mike,
Better double chek it is not a a 7-inch 45 rpm Tom Jones record.
I know Tom Jones was a British singer of the 70’s but we never watched the show. It was shown at the same hour a local singer was on TV. My mother always wanted to see the show but at home we practiced democracy where majority rules. My one years old younger brother would say, Mom, the only word he knew. My father would say local talent and so do I, we always won by the count of 3 to 1.
Best regards,
Rafael
Hi Rafael
I worked with a bulk earthworks contractor in the UK for 3 years in the late 1980s.
It was when I first used lotus 123 to its full potential in developing an average mass haul calculation matrix for cut to fill volumes.
I still have the original somewhere but it is on one of those big acetate floppies.
It was when I was developing a record keeping system that required the foremen to write a simple 3 digit code against each earth movement that I learnt my nickname - The Fat Controller.
Best regards
Mike Testro
Mike,
Very good point, your scientific approach is the correct. Production rates are not fixed.
Even when new scrapers are faster than the older they are somewhat limited, in adittion to the fact new trucks and backhoes are becoming also more efficient. We use them frequently here as our landscape is 75% mountains, on our road design and construction we accommodate for minimum hauling distances, grade-ability becomes a major concern even when empty up the hill.
Good production references should provide you with different scenarios and combination of equipment as to simplify your preliminary estimate. That is why I advocate for references that provide you with the details; usually a brief description of the operation and the crew that includes equipment will do it. This is what is missing at the production rates shown in PP, if neither crew nor methods are provided production can be anything.
Gobinath question is in order, he cannot deppend on production rates as shown in PP.
Best regard,
Rafael
Hi Rafael
Scrapers are more productive on short hauls up to 0.5 km.
Over that there relatively slow speeds become uneconomical.
Best regards
Mike Testro.
Dear Gobinath,
I would also recommend that you check the type and size of machine that you will have on site. This is a Major Factor in determining the productivity rates.
Generally, the bigger the machines, the higher the productivity rates depending on the type of site layout you have.
With kind regards,
Samer
Dont rule out moving earth with scrapers.
Thank u Mike
Hi Gobinath
It is not a good idea to leave your email address in the open forum.
Regarding your question the production rate depends mainly on the length of the haul route from your cut or borrow.
Assuming that your excavator can load 120 m3 hr then there is a formula to calculate the number of haul units.
Length of haul km x 2
Speed of haul units kmh
Volume of load m3
10 min loading + 10 min discharge.
You need to balance the number of haul units so that it will carry about 80% of the excavator production rate.
This has to be ballanced by the spreading and compaction rate and this depends on the material to be compacted.
Usually a D6 or D8 will spread the material towing a comaction unit.
Granular material can be vibro compacted
Cohesive clay has to be rolled with a colts foot or similar
Chalk is very tricky and needs special care depending on the moisture content.
Best regards
Mike Testro