Use the General tab to edit the Currency ID, Curency Name and Symbol fields to fit your national currency; do not edit the Exchange Rate field, it reflects the rate of a specific currency against the base currency,
If necessary, add a new currency to have the US dollar again
If necessary, edit the Exchange Rate field for each currency you will use against the base currency.
BE VERY CAREFULL - only an American would think that P6 is a multi-currency system. By any definition that we understand in EMEA it is NOT. You can change the symbol used, you can apply a universal factor to all amounts of money BUT with no reference to dates - so all transactions whether in the future or past are changed.
The default currency is USD. You cannot change and delete the base currency; however, you can change its ID, name, and symbol to that of a different currency to use as your base.
For example, to change the base currency to Saudi Riyal, select the base currency, type the Currency ID for SAR, enter Saudi Riyal as the Currency Name, and specify the Currency Symbol used to identify Saudi Riyal.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thanks Alexandre for the support.
Thanks
Sajid and Muhammad,
as Arnold says:
Go to Admin, Currencies,
Select the Base currency on row # 1,
Use the General tab to edit the Currency ID, Curency Name and Symbol fields to fit your national currency; do not edit the Exchange Rate field, it reflects the rate of a specific currency against the base currency,
If necessary, add a new currency to have the US dollar again
If necessary, edit the Exchange Rate field for each currency you will use against the base currency.
Click OK; it works, and well
Alexandre
Same Here
Hi Arnold,
I tried the way you are telling, but it won’t work. Neither ID nor symbolt etc, i don’t know why.
Regards,
MUHAMMAD
Hi Sajid,
Go to Admin --> Currencies --> then follow my post #3.
Regards,
Arnold
Sorry i couldnt pick from you post so please make it a bit simpler by writing down stepwise of through a screen shot
Hi Sajid,
The one I explained provides you more details. What else do you need? Please elaborate.
Regards,
Arnold
How. Please provide some more details
Sajid,
BE VERY CAREFULL - only an American would think that P6 is a multi-currency system. By any definition that we understand in EMEA it is NOT. You can change the symbol used, you can apply a universal factor to all amounts of money BUT with no reference to dates - so all transactions whether in the future or past are changed.
Hi Sajid,
The default currency is USD. You cannot change and delete the base currency; however, you can change its ID, name, and symbol to that of a different currency to use as your base.
For example, to change the base currency to Saudi Riyal, select the base currency, type the Currency ID for SAR, enter Saudi Riyal as the Currency Name, and specify the Currency Symbol used to identify Saudi Riyal.
Regards,
Arnold
Hi Sajid
P6 is American so what would you expect - anywhere outside America - north & south - or the banking system - just doesnt exist.
In PowerProject you can select any currency as a default.
Best regards
Mike Testro