P6; Activates Relationships Problem

A
Abeer Mahmoud 👤 Member for 17 years 11 months

Thanks Alexander;

It worked; I checked detailed work hours/day and made the following:

• From (0) to (7) non work

• From (8) to (15) work

• From (16) to (23) non work

I am very very happy

Best Regards,

Abeer

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Taher,

you should check the hourly detail of calendars A and B; you say that Activity # 1 starts on 8:00 AM and finishes 8 hours later at 4:00 PM: that means that this calendar does not take any lunch break into considertaion

I suspect that either the project’s or the default calendar also has 8 hours per day, but with a lunch break, and the day finishes at 5:00PM

therefore:

- Activity A goes from Day 1 8:00AM to Day 10 at 4:00PM,

- Activity B goes from Day 10 at 4:00PM to Day10 at 5:00PM, then starts its 1st complete day on Day 11 at 8:00AM

Alexandre

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi Abeer



How are the working hours of the assigned calendar? If an activity is planned until the last minute of a day, the next one will start the first hour of the following day - some constellations with milestones can behave different.



Do you have preferences equivalent to as follows?

Assigned calendar activity 1: Working time 8am to 4pm, activity 2: from 9 am to 5 pm?



Of course you can use different calendars within one project - e.g. Engineering 5d 8h, transport 7d 24h, site 6 d 10h with different holidays. But, to follow Anoon’s words, don’t exaggerate: P6 can deal, but you can’t trace.



Regards



Dieter

A
Anoon Iimos 👤 Member for 19 years 8 months

Hi Abeer,



Dieter is right, and I supposed the result of logic depends on how you had defined it.



In your example, one of your activities has 5 days duration and uses a 7 day calendar, is there logic on it?



In my opinion, it is logical to tailor your calendar(s) and resources to your activities (after all, you are assigning resources to activities and not otherwise).



And by the way, use only FS

A
Abeer Mahmoud 👤 Member for 17 years 11 months

Hi Dieter,

I agreed with you about user reference, but I mean I don’t want to face FS problem again in future and for the existing project how can I make

Activity #2; Start 11/01/2010 08:00 Finish 16/01/2010 16:00 (calendar #B; 7 working days 8hrs/day)

Instead of existing; Activity #2; Start 10/01/2010 16:00 Finish 15/01/2010 16:00 (calendar #B; 7 working days 8hrs/day)

Thanks;

Abeer

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi Abeer



What do you mean by "by default"? If you’ll work with days you must keep in mind that internally everything will be calculated in hours.

Before you’ll show a report, change your references.



Regards



Dieter

A
Abeer Mahmoud 👤 Member for 17 years 11 months

Dear Alexandre/Dieter,

Thanks for your fast replay I mad your steps and I found the following:

Activity #1; Start 1/01/2010 8:00 Finish 10/01/2010 16:00 (calendar #A; 6 working days 8hrs/day)

Activity #2; Start 10/01/2010 16:00 Finish 15/01/2010 16:00 (calendar #B; 7 working days 8hrs/day)

Activity #3; Start 15/01/2010 Finish 18/01/2010 (calendar #A; 6 working days 8hrs/day)



Well how I can solve this problem by default without need to show hours and minutes?

Best Regards,

Abeer

D
Dieter Wambach 👤 Member for 19 years 5 months

Taher



In addition to what Alexandre wrote change your user preferences to show hours and minutes:

Edit (in the menue) --> User Preferences --> Dates --> select show hours --> mark "Minutes". Then you’ll see the mismatch between calendar and your expectations.



P6 internally calculates in hours independent from what is displayed.



Regards

Dieter

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Taher,

Look at the project’s and activities’s calendar; you will certainly see that in the actvities’s calendar the day has fewer hours than in the project’s calendar; for instance 8 hours per day for the project and 7 hours per day for the activities

Alexandre

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts