Dont think thatll do it. It needs to be from task usage, but, unless Im looking at the wrong view, the left side of the screen & the table need to copy separately, and there are three rows of data in the table to each task. There has to be a better way than that degree of manual manipulation?
The report is not there. ive tried setting it up, but for some reason cant produce a task usage pivot table which shows baseline work - actual & scheduled appear no problem.
on the tool bar go to < Visual REports> and select the report you require. This will export your info to excel as long as you are using Excel 2003 or later
From my limited use of MSP 2007 so far, I personally think the "Analyse Timescales Data in Excel" macro was better in MSP 2002/03.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Brad
It is not a good idea to give out phone numbers and email addresses on the open forum.
Please use the private message service to exchange this sort of info.
Best regards
Mike Testro
Brad
Dont think thatll do it. It needs to be from task usage, but, unless Im looking at the wrong view, the left side of the screen & the table need to copy separately, and there are three rows of data in the table to each task. There has to be a better way than that degree of manual manipulation?
John
I am pretty sure I can help, but it just takes so much typing to explain it, especially without seeing it.
Is there any chance that you can send me the file so I can see what we are dealing with?
John
As I said, my use of MSP 2007 is limited and I am sure there is someone who may be able to sort this out.
Would the Budget Work Report not give you what you want ?
Sorry I cant be of any more help
Cheers
Mal
The report is not there. ive tried setting it up, but for some reason cant produce a task usage pivot table which shows baseline work - actual & scheduled appear no problem.
John
on the tool bar go to < Visual REports> and select the report you require. This will export your info to excel as long as you are using Excel 2003 or later
From my limited use of MSP 2007 so far, I personally think the "Analyse Timescales Data in Excel" macro was better in MSP 2002/03.
Regards