Maybe there was a misunderstanding - or I didnt really get your question.
WBS Summary is an acitity of the type WBS S. In the Gantt chart they will be shown as normal activities. If youll have a look at the filter "normal": task- plus resource-dependent plus WBS Summary. Study the help function to learn how to deal with this type. Important: Relationships are ignored.
I dont know how you measure progress. All the basis for progress measurement, youll attach to these activities. Then filter by "Activity Type" equal to.
Hi Arun. The easiest way to do this is to open WBS view (menu: Project->WBS). Make sure you have Gantt chart view (menu: View->Show on Top->Gantt Chart). Then right click on Gantt Chart and add Actual and Baseline bars.Thats it.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Arun
Sorry, I have no idea of what you really want.
Dieter
Dear Friends
How we are showing the actual bar of summary bar.
With regards
Arun.V
Dear Friends
How we are showing the actual bar of summary bar.
With regards
Arun.V
Dear friends
I want to know the filter method to show summaryActualprogress...
With regards
ArunV
Hi Arun
Maybe there was a misunderstanding - or I didnt really get your question.
WBS Summary is an acitity of the type WBS S. In the Gantt chart they will be shown as normal activities. If youll have a look at the filter "normal": task- plus resource-dependent plus WBS Summary. Study the help function to learn how to deal with this type. Important: Relationships are ignored.
I dont know how you measure progress. All the basis for progress measurement, youll attach to these activities. Then filter by "Activity Type" equal to.
Hope this helps.
Dieter
Hi Arun. The easiest way to do this is to open WBS view (menu: Project->WBS). Make sure you have Gantt chart view (menu: View->Show on Top->Gantt Chart). Then right click on Gantt Chart and add Actual and Baseline bars.Thats it.
Regards,
Andrew