Dear Anu,



If you are worried about the Technical side of the project, then you need to issue a letter to the Client (Request for Information).



If you are worried about the design, then you need to confirm the design worries by hiring a professional in the field and outlining the design flaw and submitting it to the Engineer.



This is a very interesting project. The Construction crews would not give you their indepth experience easily. You will need to figure a lot of the things for yourself.



With kind regards,



Samer

M
Mike Testro 👤 Member for 20 years 5 months

Hi Anu



Vladimir is the best one for this query.



However if the pipe is below the permafrost and has trace heating the cooling water should not freeze.



Fire fighting water pipes should be dry until needed.



Best regards



Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts