Hi everyone,
is there any possiblity to export the P6 calendar to Ms excel and doing the calcualtion in excel based on this calendar?
Actually, I wanted to know exactly the days completed from the BL start date till DD at WBS level taking into consideration the assigned calendar? is there anyway to know this?
Hi everyone,
is there any possiblity to export the P6 calendar to Ms excel and doing the calcualtion in excel based on this calendar?
Actually, I wanted to know exactly the days completed from the BL start date till DD at WBS level taking into consideration the assigned calendar? is there anyway to know this?
Hi everyone,
is there any possiblity to export the P6 calendar to Ms excel and doing the calcualtion in excel based on this calendar?
Actually, I wanted to know exactly the days completed from the BL start date till DD at WBS level taking into consideration the assigned calendar? is there anyway to know this?
Thanx,,,
Dieter
Arun
Have a look here:
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=67471
Dieter