Schedule Percentage complete.

A
Anbin Ponnith 👤 Member for 17 years

Dear Osama,



Using Global Change we can get Schedule % Complete in the Column Area.But I am not able to get the same in the Graphical report.I am not able to assign a custom data item as a recourse.So it could not be taken for generating graphical reports.







Is there any solution.



With Thanks & Regards,



Anbin Ponnith

S
Shah. HB 👤 Member for 17 years 6 months

Schedule percentage complete =Planned percentage completion you could do it using tool update progress as of date you need



Performance completion = actual percentage you plug in activity form and press F9



you could show both in activity column based on that you could do it in excel

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts