make a copy of the baseline first.\



Go to Project -> maintain baseline and add baseline to be added to the current project.



Then go to Project -> Assign baseline and then select the primary or user baseline.



To update program automatiucally, use spotlight tool.



To update baseline, go to project -> maintain baseline and then click update baseline button on the right hand side.