Automatic Updation

M
MK TSE 👤 Member for 24 years 3 months

Paul,



User seldom to check the display baseline bar match the original programme or not, especially if it is a large network.



Support your finding, not recommend any in-progress or completed project to be baseline

P
Paul Harris 👤 Member for 25 years 2 months

I strongly recommed against using Update Progress or the Apply Actuals function in P6 as these may change actual dates and unfortunately does not work exactly the same way as P3, SureTrak or MSP. This issue is all tied up with the Planned Dates which I would like to see removed from the software all toghether.



There is a technical article on my websites titled "Issues and Solutions facing Construction Contractors Implementing Primavera P6" which explains what happens, see slide 51.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

www.primavera.com.au - an Oracle Primavera scheduling software resources web site

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts