Revised and Recovery Programs

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Shahul,



It depends. You need to go back to the definition of a crashed schedule (increasing the resources) and check if you can use it to your advantage in the Schedule that you want.



With best regards,



Samer

S
Shah. HB 👤 Member for 17 years 6 months

Hi to all



In connection to forum topic does crashed schedule is a part of recovery or revised programme?

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Shahul,



You are correct. The reason the Engineer request a revised schedule is that the approved schedule at the start of the project does not represent the actual work ongoing at site. In most cases, you have a slow progress and the activities start and completion are late.



Therefore, in most cases, the revised schedule will indicate that the project will be completed at a later date.



With kind regards,



Samer

S
Shah. HB 👤 Member for 17 years 6 months

Samer



In connection to previous message you have mentioned In revised schedule projection completion date is flexible, in the sense it could vary from consented schedule completion date ,am i correct ?

S
Shah. HB 👤 Member for 17 years 6 months

Many thanks samer

It is very clear from your message

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Shahul,



What exactly is not clear for you. In the "Recovery" Schedule, you want to recover the lost time and maintain the end date. Crashing and Resource Leveling are planning tools to increase the productivity on the project.



Whereas, in the "Revised" schedule, you want to complete the project and the end date is flexible.



Best,



Samer

S
Shah. HB 👤 Member for 17 years 6 months

hi



I need a clarification please respond for the below message



Recovery schedule : Here we maintain same project completion date as in consented baseline but modification could be done to those activities which are yet to start or progressing by crashing and resource acceleration



Revised schedule : Here we slipped the consented project completion dated and we plan for activities which are yet to start or progressing




A
Anoon Iimos 👤 Member for 19 years 8 months

Abdallah,



Yes and No, as they might ask you to revise the schedule in order to recover.



You have to clear this out considering that when you run or calculate the schedule automatically, it will give you a result that might differ from what as planned. So in order to maintain the same timeframe (as in baseline), you need to do some modifications or revisions.



cheers

A
Abdallah Abu Ghazaleh 👤 Member for 16 years 6 months

Thank for the replies;



But what I want to clear out is that If I am asked for a revised schedule the finish date of the project will change and for the recovery it should be the same, right?

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Abdallah,



Recovery: You would rethink you schedule to come up with new methods to finish on time as much as possible.



Revised: You will revise the schedule so that the new schedule will reflect the actual progress of work at site.



With kind regards,



Samer

A
Anoon Iimos 👤 Member for 19 years 8 months

For me, a recovery program means that you may do some modifications but the new program is still aimed on the same or original target, while a revised program may have some changes that affects the whole timeframe or the scope.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts