Do they show true critical path, true float after resource leveling? I know it hung, but could you do a simpler resource leveling job, say a 2 activities job and let us know if still shows float for Critical Activities that if delayed because of resource availability the job is delayed?
Maybe even with 2 activities, not tied by relationships but by shared resources it can still be wrong as in previous versions. If not, then correct float under resource leveling with 2 activities might be all PMI requires.
Is it basically a cosmetic change, I mean 90% the ribbon?
I signed for the MSP10 beta version and am finding it to be much easier to use compared to MSP07. I will be doing a full fledge project in coming week and will post my findng.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
When I use "Group by summary" in MSP 2010, the summary task in the DURATION FIELD does not calculate as previously did in MSP2007:
Duration in Summary Task (MSP 2010) = Duration of the sub task with MAXIMUM Duration
Duration in Summary Task (MSP 2007) = Latest date of any sub task - Earliest date of any sub task
How do I overcome this problem in MSP 2010?
Click lower left corner triangle to start video.
Maybe with a single activity job they will get the correct float computation.
With resource levelling everything is the same if not worse.
Resource critical activity has free float (in 2 activities schedule!), resource constrained schedules are as poor as before.
Simple example:
Activities 1, 2, 4 have 15 days duration, activity 3 has 1 day duration, activity 5 is finish milestone.
Resource A is assigned to activities 1 and 3, Resource B is assigned to activities 2 and 4.
Activity 1 precedes activity 2 (FS), activity 3 precedes activity 4 (FS), activities 2 and 4 precede activity 5 (both FS).
Optimal duration is 31 days, MS Project duration is 45 days.
Of course it can be improved if to apply activity priorities that shall be defined manually. Again - in large projects it does not help.
Activity with obvious free float is shown as critical. Activities that are resource critical are shown with total and even free floats!
But looks nice.
Best Regards,
Vladimir
Vladimir,
Do they show true critical path, true float after resource leveling? I know it hung, but could you do a simpler resource leveling job, say a 2 activities job and let us know if still shows float for Critical Activities that if delayed because of resource availability the job is delayed?
Maybe even with 2 activities, not tied by relationships but by shared resources it can still be wrong as in previous versions. If not, then correct float under resource leveling with 2 activities might be all PMI requires.
Is it basically a cosmetic change, I mean 90% the ribbon?
Best regards,
Rafael
I tried to use MS Project 2010 to level the project that was created with MS Project 2003.
The software hanged though the same project can be levelled with the previous versions.
The problems with levelling algorithm are the same - poor results for 4 activities schedule.
I hope that final version will not hang but levelling was not improved.
Regards