I do agree; what I am saying is that MSP does not make a difference between critical tasks and critical path, it considers the critical path as the sequence of the critical tasks in a project; I am not sure the calculation option "show separate critical paths" is working properly;
by the way, MSP is not Primavera nor PowerPorject or PSNext.
If you still leave out resource critical activities it is still misleading, these are also critical activities, if you leave them out you are not complying with the definition of critical activities.
By definition resource critical activities are also critical activities, there shall be no distinction merely becaus of the reason. Resource critical makes the activity a critical activity, the resource adjective means is because of limited resources.
I do not like the PMI because they do not have the guts to make it clear, that under resource leveling these are by definition critical activities and that any software that misses these is wrong and is not up to their standards. By avoiding the issue they are doing more harm than good to their followers. At home we say to bread call it bread and to wine call it wine.
The same goes with the definition of float. A term frequently used in construction contracts. A pricise and complete definition of it is of high relevance. Avoiding due commentaries as to please those not in compliance is wrong.
the Gantt Chart Wizard does exactly the same thing that you are doing manually by Format, Bar Styles, ...
the problem is: MS Project does not update filters automatically and therefore you have to rerun the Critical Tasks filter every time you change data in the project
Vladimir,
I am not sure MS Project makes a difference between critical tasks ant the critical path, as Primavera or PSNext does or I am sure Spider does; in MSP, the critical path is built from the sequence of critical tasks
Also if your view does not higlight in red critical tasks use Format/Bar Styles for this purpose so that when showing all activities you can identify critical tasks based on color.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Alexandre,
Unfortunately the same problems exist in other packages.
Best Regards,
Vladimir
Vladimir,
I do agree; what I am saying is that MSP does not make a difference between critical tasks and critical path, it considers the critical path as the sequence of the critical tasks in a project; I am not sure the calculation option "show separate critical paths" is working properly;
by the way, MSP is not Primavera nor PowerPorject or PSNext.
Alexandre
Alexandre,
it is not rare when project has more than one critical path.
So restoring Critical Path from critical activities may become a separate task.
Rafael,
MS Project does not determine resource critical activities.
But still shows some activities as critical though they have very obvious free floats in MS Project resource constrained schedule.
The problem with PMI - it follows common American practice in PM instead of taking leadership role.
Best Regards,
Vladimir
Vladimir,
If you still leave out resource critical activities it is still misleading, these are also critical activities, if you leave them out you are not complying with the definition of critical activities.
By definition resource critical activities are also critical activities, there shall be no distinction merely becaus of the reason. Resource critical makes the activity a critical activity, the resource adjective means is because of limited resources.
I do not like the PMI because they do not have the guts to make it clear, that under resource leveling these are by definition critical activities and that any software that misses these is wrong and is not up to their standards. By avoiding the issue they are doing more harm than good to their followers. At home we say to bread call it bread and to wine call it wine.
The same goes with the definition of float. A term frequently used in construction contracts. A pricise and complete definition of it is of high relevance. Avoiding due commentaries as to please those not in compliance is wrong.
Best regards,
Rafael
Rafael,
the Gantt Chart Wizard does exactly the same thing that you are doing manually by Format, Bar Styles, ...
the problem is: MS Project does not update filters automatically and therefore you have to rerun the Critical Tasks filter every time you change data in the project
Vladimir,
I am not sure MS Project makes a difference between critical tasks ant the critical path, as Primavera or PSNext does or I am sure Spider does; in MSP, the critical path is built from the sequence of critical tasks
Alexandre
This way MS Project will show not Critical Path but Critical activities.
With resource levelling some MS Project critical activities will have free floats.
Alexandre,
Thanks, easier usually means faster and less error prone.
R. Davila
Hello,
its much easier to go to Format, Gantt Chart Wizard; in the 1st step, ask for Critical Path and click Terminate
its that easy,
Alexandre
In Gantt Chart View filter for Critical Tasks.
Also if your view does not higlight in red critical tasks use Format/Bar Styles for this purpose so that when showing all activities you can identify critical tasks based on color.
Best regards,
Rafael