P6 % Display problem

R
Rafael Davila 👤 Member for 22 years 3 months

Maybe by clicking desired column and selecting format you could get what you want, similar to Spider Project where you can save on your layouts different formats for the same column. As you can see Duration Days for Layout E is shown rounded to one decimal place while in Layout C it is shown rounded to five decimal places. In both layouts Start is shown down to the minute while Finish is shown to the second.  Because for this sample schedule 9.375 days at 8 h/d equals 75 hours so we do not see fractional hours.  I suspect you are looking in the wrong place. Similar to Excel where you can format your cells.

layout-column-formats-01



layout-column-formats-02



format-column-01  format-column-02

 

J
John Reeves 👤 Member for 13 years 1 month

I tried to follow the "settings" to round the Activity % complete to 0, I could not find it.  I did not see the settings referenced.  I am not going to set up a udf, the pct complete to 2 decimal points is crazy.

Z
Zoltan Palffy 👤 Member for 16 years 11 months

edit user preferences dates tab units format 0 decimal places durations format 0 decimals or admin preferences custom % complete 0 decimals

J
John Reeves 👤 Member for 13 years 1 month

Is this corrected in the latest version of P6?  I thought I read that it was but I cannot figure out how to get it off the two decimal reading...yes, the UDF device will work.  Come on Oracle, it has been 15 years and P6 still cannot do basic formatting that we could do in P3.  

B
Beau Wolfe 👤 Member for 10 years 7 months

Arnold,

Can you elaborate on the steps you listed above? I didn't have any luck trying to follow you.

Thanks,

Beau

D
David Kelly 👤 Member for 21 years 7 months

I have used P5/P6 since its introduction. I do not know how to do this. I agree that showing percent complete to two decimal places makes no sense to any planner. But this is a cost planning system, and the cost engineers like decimal places.

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Mohammad,



Create a UDF say, %Comp and the Data Type is "Integer".



Then create a global and rename. Select Subject Area "Activities".



Then:



%Comp = Physical % Complete



Note:

The Percent Complete is depend on what you are using whether Physical, Duration, Units or Performance % Complete.



Regards,



Arnold

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts