Progress On baseline

D
David Kelly 👤 Member for 21 years 8 months

Yes but......



Shading in baseline bars with progress is just deflection activity to disguise that fact that no earned value analysis is being done.



That’s today’s lecture over!



You need to run a global change





user_number1=BL Project Duration*Activity % Complete

And user_number1=user_number1/100.00

And user_number1=user_number1/8.00

And user_end_date=BL Project Start+user_number1

And user_start_date1=BL Project Start



Note the figure 8 is the number of hours in a day. The aboce global change needs repeated for each calander if you have calendars with different working hours.



Now you draw a user bar from start1 to end.....