There is also another way to show the cumulative number of resources.
Divide your MSP screen into 2, having the "Resource Sheet" at the top and the "Resource Graph" at the bottom.
Format your bar styles for the "Resource Graph" to be shown for "Selected Resources" (and optional: "Dont show" for "Resources").
Choose the resources you want to see the cumulative number for in the "Resources Sheet" by use of CTRL or Shift, e.g. all resources: Click first resource, hold shift down, click last resource.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Bo,
Spot on thats exactly what im after thank you very much.
Trevor,
your way has came in handy too.
Thanks again guys
Richard,
There is also another way to show the cumulative number of resources.
Divide your MSP screen into 2, having the "Resource Sheet" at the top and the "Resource Graph" at the bottom.
Format your bar styles for the "Resource Graph" to be shown for "Selected Resources" (and optional: "Dont show" for "Resources").
Choose the resources you want to see the cumulative number for in the "Resources Sheet" by use of CTRL or Shift, e.g. all resources: Click first resource, hold shift down, click last resource.
Regards,
Bo
MSP2003, View, Toolbars, Analysis Toolbar, Analyse Timescaled Data in Excel, Work
or Cumulative Work.
MSP2007, Report, Visual Reports, same thing.
Which version have you got?
Fair enough thats what i asked for lol.
could you now please tell me how i go about doing it?
ok, yes there is.