Facade - Plant Rooms interface

S
Samer Zawaydeh 👤 Member for 17 years 11 months

Dear Alex,



The best source for a solution would be your Construction Team. It depends on the site conditions and the innovative solutions that the construction team can make them happen at site.



I would highly suggest that you communicate directly with the Construction Manager and check if he can share information with you at this stage.



With kind regards,



Samer

S
Simon Martin 👤 Member for 18 years 5 months

We’ve just completed a build where we had an issue with the ventilation intakes/extracts and cladding clashing, and also scheduling the BWIC (builders work) to create the holes required.



One issue might be that if you are using unitised facade elements you need to ensure that any intakes/extracts etc. are coordinated carefully prior to the installation stage to ensure they do not clash with the joints between the facade elements.



Simon

Forum Sponsor

Top Posters

GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts