Link Remaining Duration and schedule percent complete
Forum Sponsor
Top Posters
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
hi check this formula as Rafel stated in words
% completion =[Actual duration/total duration]*100
Actual duration =[Actual start-data date]
Thanks for your comment
Look on the thread named; Updating the schedule in P3.
More often than not the progress is not as planned, especially for a job showing a 9 months delay. When progress is not as planned, linking % complete and progress is wrong because of how formulas compute remaining durations using actual durations, instead of original duration once the activity is in progress and has some duration from a prior update period. Even if the software would calculate remaining duration as a function of Original Duration, not taking into account actual duration, the computations will in most cases be wrong.
Best regards,
Rafael