Splitting / Necking in P6

A
Athar Hashmi 👤 Member for 17 years 2 months

Thanx Neil, it’s working now.

(I wasn’t doing this (necking) for every bar.)

N
Neal Walsh 👤 Member for 18 years 9 months

Athar,



By splitting, do you mean you want to stop an Activity on a certain date then commence at a later date? Or do you purely just want to ’neck’ or sausage the bars as I call em?

By right clicking the Gantt Chart / Bars / Bar Settings and then by checking the calendar non-work time box ( dont forget you have to do this for every bar you want to be necked) then this should work.....



Walshy