OD & RD Equal Zero When Converting from P6 to P3 (????)
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Ben you are not an idiot you caught the problem and solved it. I believe that during the conversion dirve activity dates by default was checked in p6 and this make the resource in p3 a driving resource.
Disregard because I am an idiot. In the Assignments window, each assignment needed to have the Resource Driving box unchecked. Problem solved.