a. have a look at Calendar Options (Tools, Options, Calendar) and consider that you have only ONE number of hours per day for each project, which means that the tasks that use the 7.5H/D calendar will be longer that one complete day, say a task starting Monday 8:00 AM will finish Tuesday 8:30 AM instead of Monday 4:30 PM; you will have to enter these tasks duration in hours instead of days to avoid mistakes
b. do you want to assign this new calendar to tasks or resources? if to tasks, open the Task Information dialog, select the Advanced tab and select the calendar in the drop-down list; if to resources, display the resource sheet, go to the Base calendar column and select the new calendar
To change the start and finish time of the day in MSP2K7:
a. create a new calendar as described before,
b. select this calendar in Tools, Change Working Time,
c. click the Working Week tab at the bottom of the dialog box, then give the week a name, such as "7.5H/D week" ("Default" by default) and a start and finish dates,
c. click Details and give each necessary day a start and finish time; I guess that you will enter 8-12 -- 13-16:30 on Friday
Click OK, OK to close all
Then, you certainly want to use this calendar in more than ONE project only? Go to Tools, Organize, click the Calendars tab, copy the new calendar from your current project in the GLOBAL.MPT file (the MSP library).
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Christian,
unfortunately, it is not as simple as that:
a. have a look at Calendar Options (Tools, Options, Calendar) and consider that you have only ONE number of hours per day for each project, which means that the tasks that use the 7.5H/D calendar will be longer that one complete day, say a task starting Monday 8:00 AM will finish Tuesday 8:30 AM instead of Monday 4:30 PM; you will have to enter these tasks duration in hours instead of days to avoid mistakes
b. do you want to assign this new calendar to tasks or resources? if to tasks, open the Task Information dialog, select the Advanced tab and select the calendar in the drop-down list; if to resources, display the resource sheet, go to the Base calendar column and select the new calendar
To change the start and finish time of the day in MSP2K7:
a. create a new calendar as described before,
b. select this calendar in Tools, Change Working Time,
c. click the Working Week tab at the bottom of the dialog box, then give the week a name, such as "7.5H/D week" ("Default" by default) and a start and finish dates,
c. click Details and give each necessary day a start and finish time; I guess that you will enter 8-12 -- 13-16:30 on Friday
Click OK, OK to close all
Then, you certainly want to use this calendar in more than ONE project only? Go to Tools, Organize, click the Calendars tab, copy the new calendar from your current project in the GLOBAL.MPT file (the MSP library).
Thats all, chap
Alexandre
Thanks a lot for your reply.
However, in my version of MS Project (2007 standard) I do not have the option to edit working times. Any ideas why this is?
The working times to the right of the calendar is grey and not possible to edit.
First of all, do not simply edit the Standard Calendar.
The Standard Calendar is 5 days/week and 8 hours per day.
If you change it you wont have a 5 x 8 Calendar anymore.
Use Tools, Change Working Time, and copy the Standard Calendar. Give it a distinctive name such as "AA 5D 7.5H".
Edit the working times, save.
Do the same thing again but name it "AA 5D 8H".
This one doesnt have to be edited because it is identical to the Standard Calendar.
You can then choose either calendar as the Project Calendar in Project, Project Information.
All Tasks use this unless you give them a different one.
You will also have to select the calendar as the Base Calendar for the Resources.