Updating the assigned base line

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Sanjay,



There are two ways on how to update your Baseline.



1. Restore your Baseline Schedule and update it in accordance to your new data date and % complete, and whatever you need to update.



2. You can update without restoring but this is more complicated than #1.



It depends on what you want to update in the "Update Baseline Options".



Regards,



Arnold

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Sanjay,



Which one do you want to update, Baseline or Revised Programme?



Regards.