How to Calculate Budget Quantity ?

I
Irfan Khan 👤 Member for 16 years 11 months
S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Irfan,



We need to under stand from you what you mean by "Budget Quantity"?



The most likely explanation is that it is the tender quantity for each line item.



The Quantities are estimated quantities that are calculated by quantity surveyors at the tender stage. It is a standard process where the tenders are reviewed and quantities are calculated depending on the Tender Documents, details, and specifications.



With kind regards,



Samer

M
Milind Pandhare 👤 Member for 20 years 9 months

Irfan

there is no Budgeted Quantity as such in P6

if you want to load Quantity as resource

Make a resource (Resource type =Material)

Asign unit for that resource (Chq Admin preferance for units)

and for a perticular activity asign that Resource with Budgeted unit =What u want

it will be the quantity for ur use

Milind

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Irfan,



I presumed you are working with Road Works. You mean "Cut & Fill" for Earthworks?





Regards.


A
Anoon Iimos 👤 Member for 19 years 8 months

cutting in cubic meters? I supposed you are going to cut concrete, is it a demolition work?



I believe you had already mentioned the budget quantity and that is in terms of m3. Or do you mean another thing?

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts