Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Anoon,



For big project, usually you have several contractors or packages working at different sections. Each project will have the following:



Scope,

Time

Cost,

Issues

Delays

Change Order

Resources

and any other specific information that is relevent to each package.



The Construction Manager needs to monitor all the project on a daily basis. The senior management at site will need the Vital Statistics of the project to be monitored on a daily basis in order to determine what is needed to achieve the target datess.



With king regards,



Samer

A
Anoon Iimos 👤 Member for 19 years 8 months

Hi Carmen,



You can tell your Client (if I may suggest), that everything is important (even the ones you considered minor foundations).



Maybe you can see (in reality) that the same efforts were exhausted to construct your massive foundations and the minor ones (the only difference is the volume).



All of that I supposed can be seen in an A4 size photo.



cheers!

C
Carmen Arape 👤 Member for 21 years 11 months

Anoon,



The client does not want an A4 size photo. He wants a brief description of the most important civil construction package.



I have only 5 important massive foundation and the rest can be consider minor or less important foundations.



Samer,



again thanks. Got your template and I will adapt to my project.



Cheers,

A
Anoon Iimos 👤 Member for 19 years 8 months

Hi Carmen,



I supposed you are working on a massive foundation.



The activities you mentioned can be done at the same time; (piles cutting; excavation; formworks; blinding or lean concrete). So don’t believe if somebody will tell you to use only "FS0"



Your excavation (clean excavation) is to fit you raft foundation. And you might forget waterproofing after you had placed lean concrete?



Yes, you can do the report in one A4. An A4 size photo would be enough to tell you what to do next.



cheers!


S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Carmen,



I sent you an email for a 1 page proposed summary. This will give you the idea.



I would suggest that you show 4 columns on 1 page. The first colum would be the summary and then one column for each Contractor.



You can show in the boxes, the summary, issues, scope, time, and cost and fill in each box 5-10 line items of specific data that you want to monitor.



With kind regards,



Samer

C
Carmen Arape 👤 Member for 21 years 11 months



Rafael/Samer



thanks for the info.



Rafael,



I am reporting civil works which mainly are in the following status:



excavation

cut-off piles

formwork and lean concrete



These 4 activities are being executed in 5 different construction packages.



I want to report in one A4 page, the status of the activities mentioned before.



At the moment, I got a report with so many pages that no one has the time to read.



Thanks again,

Carmen

R
Rafael Davila 👤 Member for 22 years 3 months

You might add:



- Permits for Construction and Inspections.

- Make sure to (within Bonds and Insurance Status Log) include all prime and subcontractor’s insurances and workmen’s comp.

- Earned Value or Progress Payment S Curve, after invoicing log.

- Safety, be careful with this issue as too much involvement might get the owner into liability.

- Photos.



Best regards,

Rafael

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Carmen,



Usually, the following information is the basic information that is shown in the monthly report:





Scope:

I. Engineering (Material and Shop Drawings)

II. Procurement

III. Construction

IV. Commissioning and Testing



Cost:

I. Invoicing Log

II. Extra Work Log

III. Variations Log



Time:

I. Approved schedule with Critical Path

II. Actual progress with updated Critical Path

III. Delays and reasons for delays



The status report should address each issue above in addition to list all the following:



1. Minutes of Meetings conducted during the month.



2. The following logs:

a. Correspondence sent and received

b. Non Conformance Records Issued

c. Material submittals status Log

d. Shop Drawings status Log

e. Procurement Log

f. Invoicing, insurance and guarantees Summary

g. Request for Information

h. Confirmation of Verbal Instructions

i. Daily reports



3. Manpower summary



4. Outstanding Issue and Recommendations



Hope that this information helps.



With kind regards,



Samer

A
Anoon Iimos 👤 Member for 19 years 8 months

Hi Carmen,



May I ask if what will you do with the sample reports? (i’m not giving you of course)



I supposed you can do your report here if you want.



cheers!

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts