I think ( and I stand to be corrected) it is to do with the zero duration value of the milestones.
You can give each milestone a 1 day duration and then mark the task as a miletone on the activity form. By doing this "progress" should roll up to the summary bar.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
You dont see 30% because thats not how MSP calculates Summary % Complete,
especially if you only have Milestones.
Even if you have, say, 10 tasks which have some duration, say 1 Day, those
10 tasks may be distributed in any of any number of ways, over any overall
duration, say 20 days, and then various of those tasks may each be not
started yet, or somwhat complete or 100% Complete.
How is MSP (or you) to calculate Summary % Complete which accounts for all
possibilities, and also always "looks right" visually?
Its a compromise. We accept the MSP Summary % Complete calculation and
dont attach much much meaning to it because there isnt much.
What if your 10 Milestones are spread across 10 days (with date constraints
or lag, or other predecessors), with, say, the 3 complete ones all at the
very start, and the others at the very end? Is 30% for the Summary still
what you expect?
I think ( and I stand to be corrected) it is to do with the zero duration value of the milestones.
You can give each milestone a 1 day duration and then mark the task as a miletone on the activity form. By doing this "progress" should roll up to the summary bar.
Cheers
Hi Asaf
When they are all set to 100% it will showw 100%.
The option in a milestone is either 0 or 100 and MSP cannot do sub percents in its summary.
PowerProject does add up completed milestones.
What sort of weird project are you working on anyway.
Best regards
Mike Testro