BQWP??

A
A D 👤 Member for 19 years 1 month

In terms of % complete, it will be



SCHEDULE % COMPLETE

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Jon,



In P6, this is the Earned Value Labor Units.



Regards,



Arnold




J
Jonathan Ward 👤 Member for 19 years 4 months

bugeted quantity of work performed!!

my next question would be, by what field is this value represented in P6?